The deadline that quietly costs you the deal

Transaction software tells you when something is due. This shows what breaks when it slips.

A dependency-graph simulator for residential deals, with the carry cost computed from a live mortgage rate.

Problem

A deal is tracked as a list of dates, but it behaves like a chain. Move the appraisal and the closing disclosure, the walkthrough and the closing all move with it — and the buyer's rate lock does not. That coupling is where money is actually lost, and no checklist shows it.

What I did

Modelled the transaction as a dependency graph with finish-to-start and start-to-start edges, lag, and anchors that cannot move. A critical-path pass computes total float for every milestone, so the tool knows which steps have slack and which are load-bearing. Every drag emits a diff, so the cascade is calculated rather than narrated.

The carry-cost figure is not a placeholder: the 30-year fixed rate is pulled weekly from Freddie Mac's PMMS series via FRED, and the exposure is arithmetic against the loan amount.

What happened

Dragging the appraisal 25 days late lands closing on day 46 — eleven days past the contract target — and expires the rate lock one day before closing, which surfaces as roughly sixty-two dollars a day of carry risk. The same drag propagates through the closing disclosure, the final walkthrough and the closing itself, and the tool lists exactly which milestones moved.

13milestones modelled
7scheduler tests
FREDlive rate feed
CPMcritical path and float